Preventive maintenance

Meyer 52-12 filler preventive maintenance schedule

A weekly, monthly, six-month and yearly checklist for the Meyer 52-12 filler, from the maintenance program World Packaging uses with its customers.

Use this as a starting point for your own program. Adjust intervals to your run hours and products, follow your plant's lockout/tagout procedures, and record what you find and replace so trends show up early.

Weekly

AreaCheckReplace or overhaul
Lift CylindersCam Rollers & Shoulder BoltsYearly
Lift CylindersAirline/FittingsAs Needed
BowlBowl Jacks (wear/binding)As Needed
Valve LeversOutside Levers (adjustment/wear)Yearly
Filling ValvesVent Tubes (loose/bent)As Needed
Filling ValvesSpreaders (damaged)As Needed
Centering DevicesRods (wear/bent)As Needed
Centering DevicesSprings (broken)Yearly
Centering DevicesBellsAs Needed
Valve OpenerShoe/Actuator (loose or binding)As Needed
Valve OpenerBottle Sensors (damage)As Needed
Valve OpenerTiming Pins (loose or damage)As Needed
Main DriveBelts for Tightness/WearYearly
Main DriveGearboxes (lube level)As Needed
Infeed DriveGearbox (wear/ lube level)As Needed
CapperSpindles (wear/torque settings)Yearly
Table TopInfeed / Discharge WearstripsAs Needed
Table TopBottle Pads (wear)As Needed
Table TopHandling Attachment (wear)As Needed

Monthly

AreaCheckReplace or overhaul
BowlLiquid Level Control (for leaks)Yearly
BowlDiaphragm Valves (for sticking)Yearly
BowlProduct Inlet Lines SealsYearly
HangerCenter Column (grease at overflow)As Needed
HangerMain Bearing Seal (damage)Yearly
HangerLube lines for damageAs Needed
HangerHardware for tightnessAs Needed
Infeed DriveU-joints (looseness)As Needed

Every 6 months

AreaCheckReplace or overhaul
Lift CylindersU CupsYearly
Lift CylindersPistonsYearly
Lift CylindersGuide Bushings/BumpersYearly
Valve LeversBushings/O-Rings/Lever SpringYearly
Filling ValvesRebuild on rotation (see note)Rotate 6 months
Centering DevicesGuide Bushings (wear/looseness)Yearly
Centering DevicesSprings (broken)Yearly
Main DriveDrive Gears (wear)As Needed
Main DriveBearings/Shafts/BushingsYearly
Infeed DriveInfeed Screw BushingsYearly
Closure DrivesDrive Gears (wear)As Needed
Closure DrivesJacuator (wear/binding)As Needed
CapperMain Bearing (binding)As Needed

Yearly

AreaCheckReplace or overhaul
Lift CylindersPiston RodsAs Needed
BowlRotary jointAs Needed
BowlSight Glass/Bowl GasketAs Needed
Valve LeversInside Levers (wear/bent)Yearly

Filling valve rebuild rotation

Rather than rebuilding every valve at once, rebuild a couple of valves each week so the whole filler is covered on a steady rotation. Inspect the sealing rubber, charging valve seat, snift seat, springs and snift stem on every valve you rebuild. We supply valve rebuild kits for Meyer fillers.